Recently, the three individual units of the Linglong Serbia Tire Factory project have passed the structural acceptance by the local government. They are BO 004, BO 004.1, and BO 005, respectively.


The three monomers are the raw material processing area of the TBR production line of the tire factory, namely the internal mixing workshop.


The total area for this acceptance is 60000 square meters. It is understood that the interior of the workshop includes a hall, technical floor, workshop, storage room, electrical room, etc.


On June 28th, its main structure completed the exterior wall closure.


The next step of the project will be to carry out internal fire protection, sprinkler, decoration and decoration work. At the same time, actively prepare for the overall acceptance of the building complex.


According to data, the investment amount of the Linglong Serbia project is $990 million (approximately RMB 6.6 billion). Its designed annual production capacity is 13.62 million sets of high-performance radial tires.